Caspian Wharf,  London SW1

 

Developer: Berkeley Homes
Consultant: PTA Consulting
Architect: Stefan Zins Associates
Contractors: Morrisroe
PSF Installer: Morrisroe
 
[Prev] [Play] [Next]

Caspian Project

'Built-in' back stop for concrete. Rapid and robust integration of slab reinforcement
>
<

Project Value:

£1,900,000 (frame)

Project Programme: 42 Weeks (frame)
Verteka Programme: 20 Days (2 days per level)
   

Key Verteka Benefits;

  • Tight programme for construction of 2 concrete frame blocks
  • 2 no E'-shaped cores constructed with Verteka reduce demand on site crane
  • Site Engineer reports ease and confidence in dimensional checks
  • Verteka providing safe, ground based access for slinging of components